2nd week pics

Onto the second week
Roadwork at the side of Balai starts
Lorries and lorries of aggregates
After Compaction
Relocate red bricks
This gonna take me whole morning
Paintwork starts, not bad not bad
Why is the football field still not complete yet >_<
Manhole

1st week pictures

FINALLY!!!!!!!!!! A working card reader. Following will be pics and pics and pics. Enjoy.
After Internal Meeting. Double rainbow. How nice.
Mmmmmmmmmm
Kelas F, 8 storeys apartments and Kelas D & E
Lokap at Balai. Left for 3 months
Balai First Floor Center Area
Canteen Area
First Floor Right Wing
Surau
Our Site Office
Bangunan Balai Polis Front View, April 5th. Gonna Change Soon
Within Lokap Lelaki. Work done by previous sub con
BRC A6 Mesh to be place internally at Lokap external brickwall
Extended Metal Mesh. Change to BRC A6 due to high cost and high in weight
 Preparation
 Example of Lokap double brickwall
Bricklaying in progress
Checking Balai Lower Roof RC Gutterdrain
Mmmmmmmm
 Plastering in progress
 Stor Barang Kes. Compaction in progress
 Thunderstorm is coming
 DRAWINGS *____*

Well Lets call it off for first week!

3rd Week

Well well, first all, sorry that I took so long to update this blog again. No internet no laptop. What to do? Cut the complaints anyway since complaining won't fix anything at all. 3rd week, so what happen?

Firstly, main task is still supervising the on going archi work within the balai. For now, work gonna stick within the lokap area. bricklaying is still ongoing as usual. Checking for the dimension and also proper construction method is the main concern, which include proper laying of damp proof membrane underneath the bricks, laying of ex-met or brick wire mesh at every fourth course of the wall, and also ensure starter bar are drilled at place needed before brick laying proceed any further. Other than that, arrange for material within the balai compound is also under my scope of work, which include keep track of the quantities, ordering, arrangement for unloading.
Plastering is going well in the lokap. The quality of work is still satisfactory.

Secondly, Structural team finally came in into the site to start their works.for the first few days, they are here to erect the scaffolding to the lower roof level. Now that they are here, means more additional task. Just nice. =_= Have to study structural drawing carefully with the sub con to every detail as the balai works cant afford to be delay any further. Being a new sub con to continue the work left over by the previous one, and me a guy who were there for just 3 weeks, things are going hectic for quite awhile. However things still goes great. So checking condition of the formwork, the rebar, the details, concrete volume to be order, and most importantly, whether the previous design had been superceded and are they using the revised version. 

Some problem pop up here and there, such as the stiffeners dimension shown in structural drawing and archi drawing do not satisfied each other. Therefore, have to consult our resident engineer and also the clerk of works, and submit request for information form if needed. Extra time before heading back home each day, help my superior in counting details such as car park and road area for whole site, total numbers of each type of windows and doors and grilles that are needed. Saturday, applied a day leave to head back to kuching to undertake MUET exam. Well, that's all for 3rd week. Till then. Well actually is "let's head to the next post"